CHIDOMASTER BLACK BELT · L6S
⚙

Chart guide

c chart

A c chart tracks how many defects turn up in the same amount of work each period: errors in a weekly audit of 100 records, faults found per inspection. It tells you whether the count has really changed, or only wobbled.

Errors in a weekly audit of 100 recordsc chart of Errors, 20 periods: average 5, upper limit 11.71, lower limit zero. One point is outside the limits: W15 (13, above the upper limit). Every other point is inside them.051015W1W5W9W13W17ErrorsUCL 11.71CL 5Errors in a weekly audit of 100 recordsc chart of Errors, 20 periods: average 5, upper limit 11.71, lower limit zero. One point is outside the limits: W15 (13, above the upper limit). Every other point is inside them.051015W1W3W5W7W9W11W13W15W17W19ErrorsUCL 11.71CL 5
Illustrative figures

Errors: centre line 5, upper limit 11.71, lower limit zero
PeriodCountSignal
W14
W26
W33
W45
W57
W64
W75
W82
W96
W104
W115
W123
W136
W144
W1513Above the upper limit
W165
W174
W186
W193
W205

Chapter 1

What it shows

Each point is a count: how many defects were found in one period's fixed amount of work. The centre line is the average count. Because counts of rare events behave in a known way, the limits come straight from that average: three times its square root either side.

One item can carry several defects, and each one counts. That is the difference from a p chart, which counts each failed item once.

Chapter 2

When to use it

Use it when you count defects and the amount of opportunity is the same every period: the same number of records audited, the same length of report checked, the same number of rooms inspected. Errors per audit, complaints per thousand contacts at steady volume, faults per inspection round.

Chapter 3

When not to use it

If the amount of work checked changes from period to period, use a u chart, which divides each count by the amount checked and plots the rate. If what matters is whether each item passed or failed, not how many things were wrong with it, use a p chart. And if the counts are large, in the hundreds, an individuals chart of the counts often fits the data better than the c chart's assumption.

Chapter 4

How the limits are worked out

Average the counts to get the centre line. The upper limit is the centre line plus three times its square root; the lower limit is the centre line minus three times its square root, and if that comes out below zero, the lower limit is zero. With small averages it usually does, which means only a high count can signal on its own; a fall has to show as a run below the centre line.

Chapter 5

Worked example: errors in a weekly records audit

A case management team audited 100 records each week for 20 weeks and counted every error it found: a missing date, a wrong code, an unsigned note. The figures are illustrative, built to show the method.

The average is 5.0 errors a week. The upper limit is 11.71, and the lower limit works out at minus 1.71, so it is set to zero. Week 15 found 13 errors, above the limit: a special cause. Every other week sits between 2 and 7, with no long run on either side of the centre line.

Week 15 is worth a conversation; weeks 4 and 5, with five and seven errors, are not. If the team wanted fewer errors overall, the chart says that chasing individual weeks will not get there: the process produces about five errors per hundred records as a matter of course, and only a change to the process itself, such as a required field or a checklist at the point of entry, will move the centre line.

Chapter 6

The arithmetic

Two steps: the average count, and the limits from it. Stated in words first, then written out, then worked with the 20 weeks above.

The centre line is the average number of errors found per audit.

cˉ=1m∑j=1mcj\bar{c} = \frac{1}{m}\sum_{j=1}^{m} c_j
cjc_j
errors found in week jj
mm
the number of weeks, here 20
cˉ\bar{c}
the average count, the centre line
Worked with this page's numbers
  1. cˉ=100÷20=5.0\bar{c} = 100 \div 20 = 5.0 errors a week

For counts of rare events the spread follows from the average itself: the standard deviation is its square root. The limits sit three of those either side of the centre line, and a lower limit below zero is set to zero.

UCL, LCL=cˉ±3cˉUCL,\ LCL = \bar{c} \pm 3\sqrt{\bar{c}}
cˉ\sqrt{\bar{c}}
the standard deviation of a count whose average is cˉ\bar{c}
Worked with this page's numbers
  1. 5.0=2.236\sqrt{5.0} = 2.236, so 3cˉ=6.7083\sqrt{\bar{c}} = 6.708
  2. UCL=5.0+6.708=11.71UCL = 5.0 + 6.708 = 11.71
  3. LCL=5.0−6.708=−1.71LCL = 5.0 - 6.708 = -1.71, below zero, so zero
  4. Week 15 found 13 errors: 13>11.7113 > 11.71, outside the limit

Chapter 7

How to make one in a spreadsheet

One row per period with its count. Average the counts, take the square root of the average, and work out the two limits. Draw the counts as a line with the centre and limits as flat lines. Keep the amount checked the same every period, and write it on the chart; if it has to change, switch to a u chart.

Chapter 8

Where it fits in a project

In Measure it sets the baseline for an error count, and it often feeds a Pareto chart: the c chart shows how many defects there are and whether the count is stable; a Pareto chart of the same defects by type shows which kinds to work on first.

Fewer errors, for good

A free 30 minute discovery call. Bring your audit counts, and we will see whether the answer is the weeks or the process.

Book a free discovery call