Our own project · Meridian Hospital Group is a constructed operator; the instrument and its figures are real
Meridian Hospital Group · Method
You cannot improve a hospital that does not exist
Two methods share four letters and are routinely argued about. Underneath the argument they are the same discipline: state where you are, state where you need to be, and close the distance. What changes is not the goal but where you have to look to find the current state, and the answer for a hospital that does not exist yet is not nowhere.
This study has been running one of these two methods for its whole length without naming it, and the choice was not obvious at the start. It is worth setting out the distinction properly, because it explains why the work looks the way it does and, more usefully, when it would have been wrong.
The distinction is usually made in acronyms. It is better made in a sentence: a new design starts from nothing and goes to the dream, and work on an existing thing does whatever it takes to turn what you have into what you want it to be. Everything below follows from that, including the test for which one you are actually in.
Chapter 1 · The difference is the starting point
Start from nothing, or start from what you have
Put plainly, and better than the textbooks put it: a new design starts from nothing and goes to the dream. Working on something that exists means doing whatever it takes to turn what you have into what you want it to be.
The destination is the same in both, and in neither case is it a fantasy. A dream is what you want subject to the real world: what the ground will carry, what the grid will supply, what the regulator will licence, what the market will pay and which clinicians actually exist. A dream that has not been ground against those is not a brief, it is an aspiration, and the commonest failure of a new build project is discovering the difference at tender.
So both cases are constrained and they are not constrained by the same things. Working on something that exists means carrying two layers: the real world, and the decisions somebody else took and fixed in place. A new design carries one. The difference between the two methods is precisely that inherited layer, and it is the only difference that matters.
That is why starting from nothing is the freer case and not the easier one. Nothing has to be accommodated and no decision from 1987 has to be worked around, which sounds like an advantage and is mostly an absence of excuses. Everything this study spends twenty pages on, from land title to water table to road speeds to the paying share to the fire brigade response time, is the real world arriving to bound a dream that started out unbounded.
And the constrained case has a ceiling that the free one does not. Doing what it takes has a limit set by what is already there, which is what the rest of this page is about calculating before anybody commissions a programme that assumes there is not one.
Chapter 2 · The correction that collapses the argument
Both are AS IS to TO BE, and the current state always exists
The distinction between the two methods is real and it is smaller than the literature makes it, and it is worth collapsing before it does any damage.
Both are the same discipline. Establish the current state honestly. Establish the required state precisely. Close the distance between them and then hold it. Everything else, including which five letters are used, is a question about what kind of intervention closes that particular distance.
Which exposes a mistake that this page made in an earlier version and that design projects make constantly. It is not true that a design project has nothing to measure. The current state always exists. It simply is not inside the facility that has not been built.
For this project the current state is not an empty field outside Lagos. It is a family selling something to buy three plane tickets, a consultant in Ibadan writing a referral to a hospital four thousand miles away, and a billion dollars a year leaving the country. That is a process. It has a cycle time, a cost, a failure rate and a set of customers who can describe it in detail, and every one of those is observable today without anybody laying a brick.
So the Measure phase of this study was not skipped and it was not substituted. It was run, and what it measured was the process people use when the thing they need does not exist. The patient page, the family testimony and the outbound flow figures are not context or colour. They are the AS IS.
That changes what the model is for, which is worth being precise about. It does not stand in for observing the current state, because the current state was observed. It stands in for observing the future state, which is the only one that genuinely cannot be watched before it is built. A run predicts the TO BE. It does not excuse anybody from measuring the AS IS.
And it supplies the test the earlier chapters are really applying. A project that cannot describe its current state in measurable terms has not finished Define, whichever method it thinks it is using. A project that can describe the current state but not the required one is about to improve something toward no particular destination. Both failures are common, both are visible from outside in about ten minutes, and neither has anything to do with which acronym is on the front of the report.
The current state of this process, in the words of the people using it, is on why we still fly.
Chapter 3 · Side by side
The five phases, which share four letters and diverge at the second
The two sequences look similar enough that the difference is often treated as terminology. Read the last column, because the divergence is real and it is largest exactly where it is least noticed.
The second row is the one that matters. In an improvement project, Measure means observing a process that runs: how long things take, how much they vary, where the waiting is. It is the phase that supplies the evidence for everything after it, and it is evidence in the ordinary sense, because somebody watched.
The second row is where the two are usually said to diverge most, and the divergence is narrower than that. In an improvement project Measure observes the process inside the thing being improved. In a design project it observes the process people are using instead, because there is always one, and then adds the requirement translated into characteristics the new design can be tested against. Both are observation of a current state. Only one of them finds it in the building it is about.
What a design project genuinely cannot observe is the future state, and that is what the model is for. It predicts the TO BE. It is not a substitute for measuring the AS IS, and a project that uses it as one has quietly skipped the only phase that produces evidence rather than intention.
| Phase | Improving something that exists | Designing something that does not | What actually changes |
|---|---|---|---|
| Define | The problem, the boundary of the process, and how badly it is currently performing. | The requirement. Who the customers are, what is critical to them, and what the thing being built has to achieve. | From a problem statement to a requirement specification. One describes a gap, the other describes a target that does not yet have anything aimed at it. |
| Measure | The process as it actually runs: capability, variation, where the time goes. Observation of the thing itself. | The process as it actually runs, which is whatever people currently do instead. Plus the requirement, translated into characteristics the new design can be tested against. | Not as much as usually claimed. Both measure a current state. Only one of them finds it inside the building it is about. |
| Analyse | Root causes of the gap between current performance and requirement. | Alternative designs, compared against the characteristics, before any of them is developed. | From causes to options. One asks why this is happening, the other asks which of these would work. |
| Improve, or Design | Remove the causes, pilot the change, confirm it moved the number. | Develop the chosen design in detail, model it, and establish that it can be built and operated. | From intervention to creation. An improvement is reversible and a design is not, which is why the phases before it matter more here. |
| Control, or Verify | Hold the gain. Monitoring, a documented standard, and an owner who will notice when it drifts. | Prove the design meets the characteristics before it is handed over, and then hand it to Control. | From sustaining to proving. Verify is the phase that does not exist in most building projects, which is why operators inherit buildings nobody demonstrated would work. |
summary: the same five steps in name only. The last column is where the two methods actually diverge, and the second row is where projects most often pretend they are doing one while doing the other.
Chapter 4 · Entitlement, and why nobody calculates it
The test: how much of the gap is even reachable
Three numbers decide which method applies, and only two of them are ever produced.
Current performance is measured constantly. The requirement is usually stated, sometimes carelessly. The third is entitlement: the best this design could do with every special cause removed, every process running properly, and nothing changed physically. It is what the building and the configuration will allow at their theoretical best, and almost nobody calculates it, because doing so means writing down what the existing design cannot do.
With it, the question answers itself. The part of the gap that sits below entitlement is improvement work and it is available. The part above it is not available at any effort, because it is a property of the design rather than of the process running inside it.
Look at what that does to the four measures above, and at how badly the size of the gap predicts the answer. The largest gap on the list is half reachable, because the lift core caps how many patients can move before noon. The smallest is entirely reachable. Nurse walking has a large gap of which barely a quarter is available, because the distance between a bed and a store is a constant. Theatre cancellations look intractable and are entirely a policy matter, because ring fencing a list costs nothing physical.
Two of those four are improvement problems and two are design problems, and nobody could tell which by looking at the numbers everybody already has. That is the argument for calculating the third one.
Where the entitlement figures come from, and how to measure them in an existing building, is on after it is built.
| Measure | Now, and the best this design allows | What is required | What that means |
|---|---|---|---|
| Discharges completed before noon (%) | 20 now, entitlement 45 | 70 | Improvement can reach 45, which is 50% of the gap. The remaining 25.0 is not available at any effort, because it is a property of the design. |
| Time from arrival to a bed (hours) | 8 now, entitlement 3 | 4 | Entirely inside the entitlement. This is improvement work and a redesign would be an expensive way of avoiding it. |
| Nurse walking per shift (km) | 6 now, entitlement 5.2 | 3 | Improvement can reach 5.2, which is 27% of the gap. The remaining 2.2 is not available at any effort, because it is a property of the design. |
| Theatre lists cancelled per week | 6 now, entitlement 1 | 1 | Entirely inside the entitlement. This is improvement work and a redesign would be an expensive way of avoiding it. |
derived: stated current performance, entitlement and requirement for each measure. Entitlement is the estimate that actually decides the question and it is the one nobody usually makes, because it requires admitting what the existing design cannot do
Chapter 5 · The failure this test prevents
Improving against a constant
The failure mode worth naming is the one that follows from skipping the entitlement calculation, and it is depressingly orderly.
An operator is set a target above what the building allows. An improvement programme is commissioned, competently, and it delivers: the reachable part of the gap closes and performance improves genuinely. It then stops, because it has arrived at the ceiling. The target is still missed.
What happens next is the damaging part. The shortfall is attributed to execution, since the method is known to work and the team clearly did not achieve the target. A second programme is commissioned. It delivers nothing, because the first one already took everything that was available. The team learns that improvement work is theatre, the organisation learns that its staff cannot deliver, and nobody involved has done anything wrong.
This is the same structure as the appraisal problem on the constants page, arriving from the methodological side. An operator measured against a performance whose ceiling somebody else set will look like a poor operator, and the only thing that distinguishes a low ceiling from a bad team is the number in the middle column of that table.
Which gives the rule in one sentence. Before commissioning improvement work, calculate the entitlement, and if the requirement sits above it then the honest answer is that this is a capital problem wearing an operational costume, and no programme will fix it.
Chapter 6 · Which is the whole of the obligation
Today’s dream is tomorrow’s existing
There is one consequence of that framing which deserves stating on its own, because it is the reason a design project carries a heavier duty than an improvement project rather than a lighter one.
The dream stops being a dream on the day it opens. From that morning it is simply what somebody has, and everybody who comes after is in the second case: doing what it takes to turn what they have into what they want. Every freedom exercised during the design is converted, at handover, into a constraint that a stranger will spend decades working around.
So the new design is not choosing a building. It is choosing which of the real world constraints get absorbed now and which get handed on, and therefore the entitlement of every improvement programme that will ever be run inside it. A ward drawn slightly too long does not fail; it sets a ceiling, and somebody in 2049 will commission work against that ceiling, deliver the reachable part, miss the target and be judged to have underperformed.
That is what makes the freedom uncomfortable rather than pleasant. The person who will pay for a decision taken now has no way to object to it, cannot be consulted, and in most cases has not been born into the profession yet. The only thing that represents them at the table is whether anybody writes down what was chosen and why.
It also settles what a design project owes the operator, which is not a finished building. It is a stated entitlement: here is what this configuration can do at its best, here is the evidence for that claim, and here is the list of the things we fixed in place that you will not be able to change. An operator handed that document can tell the difference between a management problem and a capital one on their first day, which is the distinction the rest of this page exists to protect.
What gets fixed, and what undoing each one would take, is on after it is built.
Chapter 7 · The phase most often dropped
Verify is not Control, and the difference has an owner problem
The last phase differs in a way that sounds pedantic and is not.
Control holds a gain that has already been demonstrated. The change was piloted, the number moved, and the work is to stop it drifting back: a standard, a measurement, an owner who notices. It is a maintenance activity and it belongs to whoever runs the process.
Verify proves that a design meets the characteristics it was built to satisfy, before anybody relies on it. It is not maintenance, it is evidence, and it happens once, at the point where a thing is handed from the people who made it to the people who will live with it.
In building projects that phase mostly does not happen. There is commissioning, which demonstrates that the systems work, and there is handover, which transfers responsibility. Neither of them asks whether the finished hospital achieves the characteristics stated at the beginning, and the reason is that the question has no owner: the designer has finished and the operator has not arrived.
Which is what the sixth gate on this project is for. It is the point where Verify hands to Control, and it never closes, because the only instrument capable of verifying a hospital is the hospital running. Everything measured after opening is simultaneously the proof that the design worked and the baseline for holding it.
The gates, and the one that stays open, are on the solution stream.
Chapter 8 · And what each phase could not do
Where this project sits, phase by phase
The whole study mapped onto the five phases, which also makes it navigable, since the pages were written in this order without the order being announced.
The last column is the point of the table. Every phase here has something it could not do, and in each case the limitation is a consequence of designing rather than improving: no process to measure, a decisive input that stays unmeasured, a design that is a shape rather than a specification, and a verification that can only see what somebody thought to model.
Naming those is not modesty. A design method that does not state what its evidence is missing produces the same confident output as one that has the evidence, and the two are indistinguishable from outside.
| Phase | What it was on this project | Where it is written up | What it could not do |
|---|---|---|---|
| Define | The instruction: the question, what is already known, the comparators, the criteria and weights, and what a complete answer must contain. | Instruction 01, and the criteria fixed in it before any answer existed. | It could not state a bed number or a site area, and it was right not to. Those are outputs of the later phases and a Define that names them has skipped to the answer. |
| Measure | The current state, which is the process people use instead: flying out, paying out of pocket, and what it costs them. Plus the requirement, from the patient, the family and the staff. | The patient page, why we still fly, what a hospital is for, and the outbound flow in the instruction. | It could not measure the future process, which is the one thing no amount of fieldwork reaches. That is what the run is for, and the run predicts rather than observes. |
| Analyse | Alternatives compared: two comparators, five plan forms, the stack, catchment against city, the three streams, the layered power options, seven controls on supply. | How big, land, massing, entry flow and exit, power and infrastructure, fake drugs. | It could not settle the paying share, which is the term with the most leverage over every one of those comparisons and the reason several of them end in a range. |
| Design | The plane and the stack, the schedule of accommodation, the standards re-derived for this climate and this grid, the supply and automation strategy. | Massing, standards, automation, just in time. | It is not detailed and does not claim to be. What exists is the shape of the design and the constraints it has to satisfy, which is what the gates before it need. |
| Verify | Running the whole hospital, across its life rather than the holding period, before the concrete is poured. | The solution stream, and the sixth gate that never closes. | It cannot see a failure arriving from a direction nobody modelled, which is stated there and is the permanent limit of the method. |
summary: where each phase of this project sits, and what each one could not do. The last column is the honest part.
Chapter 9 · Three, published with it
Where this falls short
Three, and the first undermines the central argument of the page, which is the right place to put it.
The entitlement test decides everything and entitlement is never observed, because a process almost never runs at its theoretical best. So it is estimated, and it is estimated by people who usually have a view about whether the answer should be a redesign. The defence is to derive it from physical constants rather than from performance history: lift capacity, walking distance, plate depth and compartment size are measurable, they do not have opinions, and they bound the entitlement whether or not anybody likes where the bound falls.
-
Entitlement is an estimate and it decides everything
Falls short- Where it is weak
- The whole test rests on knowing the best the current design could do with every special cause removed. That number is never observed, because a process almost never runs at its entitlement, so it has to be estimated, and the estimate is made by people with a view about the answer.
- Who carries it if we are wrong
- Whichever side of the decision is wrong: a redesign that was not needed, or a decade of improvement work against a ceiling.
- What would settle it
- Estimating it from the physical constants rather than from performance history, which is what the survey on the constants page is for. Lift capacity, walking distance and plate depth are measurable and they bound the entitlement whether or not anybody likes the answer.
-
The verify phase has no natural owner
Falls short- Where it is weak
- Proving a design meets its requirements before handover falls between the designer, who has finished, and the operator, who has not arrived. It is the phase most often dropped, and dropping it is invisible at the time because nothing goes wrong until the building opens.
- Who carries it if we are wrong
- The operator, who inherits a building nobody demonstrated would work and is then appraised on its performance.
- What would settle it
- Naming the owner at the first gate and keeping them across the handover, which is the same person the constants page argues does not currently exist in most programmes.
-
Design work is slower and its benefit is counterfactual
Accepted cost- Where it is weak
- A design method costs more before anything is built and its return is a set of problems that never happened. That is the same measurement asymmetry as every buffer in this study, and it fails in the same way, to the same argument, in the same kind of meeting.
- Who carries it if we are wrong
- Whoever has to defend the front loaded cost against a schedule.
- What would settle it
- Nothing settles it. Writing the reasoning down at the point of the decision is the only defence, and it works about as well here as everywhere else it has been proposed on this site.
The instruction this method was applied to
Define, in the form this page argues for: a requirement, a boundary and a grading, with no answer in it.
Read instruction 01